SR 27/32nd Ave. to Trent Ave.- Grind out top layer of roadway and resurface with Hot Mix Asphalt. Construct ADA sidewalk ramps.
14th Ave from Custer to Carnahan – lane
restrictions from 7 a.m. to 5 p.m. until October 14 for a stormwater upgrade
project.
around the clock until the end of October for sidewalk improvements.
Drivers are redirected via Evergreen or Progress.
lane each direction until late-October for street resurfacing.
lane each direction starting Monday, October 7 at
6 a.m. until late October.
of October for sidewalk updates and improvements.
SPOKANE CITY
Greene St. Bridge Work- A project to increase
the life of the Greene Street Bridge over the Spokane River is under way.
Through mid-October, anticipate lane restrictions on the
bridge and on Greene Street between South Riverton Avenue and Upriver Drive. The
work on the bridge will improve its load rating, allowing larger trucks and
loads to use the bridge. The project includes installing fiber-reinforced
polymer to the bridge deck and floor beams. Additionally, utility conduit
will be installed along the underside of the bridge and other related work will
be completed.
Maple St. Bridge Work Starts Tuesday- Bridge crews will close one south bound lane Tuesday, October 8 through Thursday, October 10, 9
a.m. to 3 p.m.
Stevens St. Lane Closure- Stevens Street between
Main and Riverside Ave. will have two southbound lanes closed 24 hours a day
for Avista work through Monday, October 14.
Wall St. Closure Saturday- Wall Street between
Sprague and 1st avenues will have full closure, Saturday, October 5, 6 a.m. to 6 p.m. for work at 705
west 1st Avenue.
Crestline Rehabilitation Project Nearly Finished- Paving is currently
underway. This project replaces the water main in Crestline
from 37th to 57th avenues; provide curb-to-curb
rehabilitation of the street from 44th to 53rd avenues;
and add bike lanes, sidewalks and stormwater swales along the 44th
to 53rd avenue stretch.
Rockwood Blvd. Rehabilitation Nearing Completion- Paving
begins next week with the project being substantially complete in the next
two weeks weather permitting. A project to rehabilitate Rockwood
Boulevard from Cowley to Southeast Boulevard and Upper Terrace Road from
Rockwood Boulevard to 17th Avenue continues.
14th Ave. from Lincoln to Grand- This
project, to rehabilitate 14th Avenue from Lincoln to Grand
Boulevard. Paving of 14th from Grand to just west of Division,
is substantially complete. The street is paved and open to traffic.
Traffic Calming Work- Work on a variety of improvements to promote traffic calming throughout the City has begun and will continue through October. The following streets are affected:
Illinois – Signs
and striping
Mission, Cook and
Regal – Ramps and striping
Manito Boulevard
and 29th – Ramps and striping
37th
from Bernard to Browne – Sidewalks
Maple from 8th
to 9th – Bumpouts
Adams Street from
Montgomery to Mansfield – Sidewalks and ADA ramps
Horizon Avenue
and F Street – Sidewalks and ADA ramps
Maple Street from
Chelan to Fairview – Sidewalks and ADA ramps
Ash Street from
Fairview to Cleveland – Sidewalks and ADA ramps
Liberty St. Construction-
Construction to
rehabilitate Liberty from Oak Street to Ash Place and Ash Place from Liberty to
Dalton is beginning. The road is closed with local access only.
Post St. Closure- Post Street near
City Hall will close for Avista work
on City Hall Plaza and new crossing work between City Hall Plaza and Riverfront
Park. Crews will use this closure to work on sidewalks at the southwest
corner of the Post Street bridge, a new Centennial Trail connection into
Riverfront Park, additional sidewalk work on the west side of Post Street and
for the re-striping of Post street.
Fiske St. Construction- This
project will pave Fiske Street from 19th to 17th avenues, install curbs,
sidewalks and ADA curb ramps, where needed, and replace current or
install new stormwater drainage, where needed. The project will place pavement between the existing curbs on
Fiske from 17th to 18th and install new curbs and
sidewalks, and pave on Fiske from 18th to 19th. Fiske is closed between 17th and 19th
streets.
Third Ave. from Division to Arthur- Work to rehabilitate Third Avenue from Division east to Arthur is
currently being paved. Arthur and Sherman continue to be the detour
route with periodic closures on one or the other street as needed. The
project also includes replacing a 12-inch water main. Local access to
businesses will be maintained. Work will continue into October.
Euclid Ave. Water Main Project- This
project will replace the current 28-inch water main with a 30-inch water main
in Euclid Avenue. The new main will begin at Euclid & Mayfair and
continue to Crestline, with a jog to the north around Gonzaga Prep High School.
Local
access only on Euclid from Nevada to Mayfair and on Dalton from Crestline to
Perry.
SPOKANE COUNTY
Farwell Rd. from Market to North Spokane Corridor– Closed for fall.
Bruce Rd., Peone to Day Mt. Spokane Road- Road is open on weekends, closed during the week.
Pittsburg Rd at intersection with US 2– Closed for sewer work.
Johansen Road, from Prairie View Elementary to Northview Lane- Closed for sidewalk installation and road widening.