WSDOT
from about 8 a.m. until 3 p.m., drivers on northbound Nevada Street may see lane
restrictions at the intersection as crews are working on the pedestrian trail.
Vicinity Signage Upgrade- Be alert for equipment and
workers on the shoulders with possible shoulder restrictions or lane
restriction as crews replace old signs. All ramps will be open. No delays expected.
Structures/Realignment & Ped/Bike Trail Extension- Possible intermittent
short delays with flaggers directing traffic at the Freya St. roundabouts. Flaggers will be stopping traffic intermittently to
allow trucks in and out of the work site or during times of overhead work on
the Pedestrian bridge.
SPOKANE CITY
Browne Street Closure- Browne Street will be closed from Sumner to 13th for sewer and
water connections until
May 8.
Nevada Lane Closure– Crews will be installing PVC for Comcast from May 4 to May 8 at 9911 N. Nevada. The western southbound lane will be closed.
Grand Boulevard Closure- The northbound right lane and sidewalk on Grand Boulevard from Rockwood to Sumner will be closed on May 4 for fiber splicing.
I90 Division Gateway Ramp Closure- This project is for beautification
improvements to five locations at the I90 and Division Street
gateway entrances to the City. The westbound I90
off ramp will be reduced to one lane next Tuesday to Thursday nights, May 5 – 7.
SPOKANE VALLEY
Sullivan Road Bridge Replacement Project Area-
- Traffic remains reduced to one lane in each direction
around the clock from Indiana Avenue to the Sullivan Park signal Monday
May 4 through Wednesday May 6. - Southbound Sullivan Road
bridge will close Thursday, May 7 through the end of the year and
into early 2016 for bridge demolition and replacement. All
traffic will be shifted onto the northbound bridge with one lane
northbound and two lanes southbound between Indiana Avenue and the
Sullivan Park traffic signal. - Turns from Indiana onto northbound Sullivan will remain
reduced to one lane through the end of the year and into late 2016/early
2017.
University at Appleway Intersection- University at Appleway remains reduced to one lane in each
direction until May 9 for work on the Appleway
Trail. Appleway at University remains reduced to two lanes for median work.
Residential Street Sweeping- Expect street sweeping vehicles in residential areas
throughout the city Monday-Friday from 7:00 am – 5:00 pm through May.
SPOKANE COUNTY
Christensen Road Bridge- Complete road closure on Monday, May 4 to start work to replace the existing bridge. You can view the detour here.