SPOKANE COUNTY
Country Homes (Wall to SR 395)- Stormwater work in the raised islands, install topsoil.

Look for occasional lane closures for cleanup work. On-street parking is limited.

Geiger Blvd./Westbow Blvd. (between Thomas Mallen Road & Soda Road)- Geotechnical core drilling. Lane restrictions with flaggers.

61st (Palouse Highway to Yale Road) and Ben Burr Road (from 57th to 65th)- Road reconstruction & waterline installation. Road closure; detour in place.

Barker Road (11th Ave. to 15th Ave.)- Road work and widening. Lane restrictions, watch for flaggers.

WSDOT
No work at this time.


SPOKANE CITY
37th Avenue, Regal to Custer Streets- 37th Avenue between Freya Street and Custer is open. 

Landscape work addressing
safety issues is being completed, the remaining landscape work will be
completed in the spring of 2017. This work is to reconstruct the road, include pavement
replacement, curbs, sidewalk, bike lanes, stormwater piping, and a 36 inch
water main.
Adams Street Combined Sewer Overflow (CSO) 24- Construction
on CSO 24 will start in January. Preliminary work begins now with CenturyLink placing conduit and cable on Adams Street between Sprague
Avenue and 1st Avenue through Wednesday,
December 14. This
project will construct a 2,000,000 gallon Combined Sewer Overflow Tank (CSO)
tank and piping.
Bridge Avenue and Monroe Street CSO Work- Summit
Blvd./Bridge Ave. is closed. Lincoln
has one northbound lane open.  Lincoln southbound is closed at Broadway
with local access maintained to Anthony’s restaurant. This
project will construct a Combined Sewer Overflow Tank (CSO) tank.
Pettet DriveTJ Meenach Combined Sewer Overflow (CSO 12) Project- Pettet
Drive is closed to traffic.  The clover leaf that services TJ
Meenach, Down River and Pettit Drive is in service. The leg that comes off of Pettit northbound will re-direct citizens to Northwest Blvd. Vehicles traveling southbound
on Down River Drive have two options; enter onto TJ Meenach or continue under the bridge and turn
uphill to Northwest Blvd. This
project will build a 690,000 gallon storage facility and connections to
existing CSO Basin 10 outfall.  Work also includes repaving of Pettet
Drive and pedestrian/bike trail construction.
SPOKANE VALLEYSullivan Road Bridge – On weekdays from dawn to dusk, expect
traffic to be reduced to a single lane northbound and expect turns from Indiana
onto northbound Sullivan to be reduced to one lane. 
Translate (Traducir/Перевод) »