WSDOT

SR 902 Delays- Anticipate delays Saturday, June 18 on SR 902 from the I-90 Salnave Interchange into Medical Lake. Community events will be underway with a signed detour in place.
US 2-Division Street/Curb and Sidewalk- Division Street is reduced to two lanes for curb and sidewalk improvements.  Drivers may experience congestion and delays.
I-90/Sunset Hill to Argonne- Sunday through Thursday, June 19-22, during daytime hours, WSDOT Maintenance crews will be sweeping I-90 in the Spokane metro area at various locations, possibly in the far left or far right lanes or shoulders. Be alert for lane restrictions and possible slow traffic with workers and equipment adjacent to traffic.  
I-90/Westbound Freya Off-Ramp- On Monday, June 20, beginning at 7 p.m., westbound
I-90 will be reduced to two lanes.  At 11 p.m., westbound I-90 will
be reduced to one lane. Lane restrictions will be in place until as
late as 3 a.m. Tuesday morning.  Westbound drivers should expect slow
traffic and congestion during these hours. Work is underway to construct a new westbound Freya Street off-ramp approximately 1/4 mile to the east of the current ramp. There are no mainline freeway impacts.  All ramps are open.  Expect lane restrictions on 2nd Avenue.
I-90/Appleway Westbound Off-Ramp- On Wednesday, June 22, from about 9 a.m. until as late as 4 p.m., the Appleway westbound off-ramp will be closed for repairs to bridge approaches.  This is the partial interchange to the west of Liberty Lake.
US 395-Division Street/Hawthorne Rd. Intersection- Beginning Wednesday, June 15, be alert for turn restrictions on Division as Spokane County work has Hawthorne Road closed between Division and Waikiki.

SPOKANE VALLEY

32nd
Avenue from Dishman-Mica Road to University Road
– Closed through mid-August for street preservation work. Signs detour traffic via Dishman-Mica Road and University Road.
 32nd Avenue from University Road
to Pines Road
– Reduced to one lane in each direction through mid-August. The north sidewalk is closed. Anticipate brief interruptions to side streets and driveways from
7 a.m.-5 p.m.
 Fancher Road between Trent Avenue and Sharp
Ave
– Traffic is reduced to one lane in each direction through early July.
Southbound Sullivan Road Bridge- Traffic remains
reduced to one lane northbound and two lanes southbound. Turns from Indiana
Avenue onto northbound Sullivan Road are reduced to one lane. Southbound Sullivan
Road at Flora Pit Road will be reduced to one lane on weekdays through Friday,
June 24 from 6 a.m. to 2 p.m.


SPOKANE COUNTY

Market Street
(Parksmith to Farwell)
Road closed with a detour in place to rehabilitate the roadway and add fiber optic and sewer components.
Seven Mile Bridge
& Seven Mile Road-
The road is closed with a detour in place while the bridge is removed and replaced. The speed limit has been reduced to 25 miles per hour during this project.  
Hawthorne Road West
(Waikiki to US395)-
The road is closed until the end of august for road rehabilitation, installation of stormwater drainage swales, tree planting, irrigation components, curb construction, traffic signal improvement, bike lane installation and striping.  
Hawthorne Road East (US395
to US2)-
Roadway rehabilitation including stormwater sand filters, curb construction, traffic signal installation, bike lane installation and striping.
Bigelow
Gulch Road from Havana to Argonne- 
Crews will work on
Bigelow Gulch Road from Havana to Argonne starting Monday, June 20 through Thursday,
June 23. The work consists of asphalt overlays. A pilot car will lead traffic in both
directions with possible delays of up to
20
minutes. 
Houston
Road from Colville Road to Grove Road- 
Crews will be working on
ditching, culvert and shoulder work during day hours only. The road remains open.

SPOKANE CITY
Post Street Closure- Post Street will close at noon Friday, June 17 for
Terrain’s Bazaar between Spokane Falls Blvd and Summit Parkway. The closure is
scheduled to last through midnight on Saturday, June 18. There will be no
parking on Post Street. 

Carlisle Street Closure- The General Store’s Car Show will close Carlisle between
Division and Ruby on Saturday, June 18 between 7 a.m. and 1 p.m.

Hatch Road Grinding- Crews will be grinding Hatch Rd. starting Monday, June 20 at
57th, working downhill. There will be a lane closed with flaggers.
High Drive Phase II, Bernard to Grand Street Repair Work- Work
began Monday, June 13, for repairs along High Drive.  Traffic restrictions
are in place and flaggers are on site to direct traffic.
·     Main and Division Intersection Improvements- Work
continues on sidewalk removal and excavation for underground storm water
improvements.  Pedestrian detours are in place. Throughout
the project there will be lane restrictions on both Main and Division.  Traffic control will be in
place. 
Work
on this project involves curb bumpouts at all four corners of Division Street
and Main Avenue, the removal and replacement of existing curbs, gutters, and
sidewalks, ADA upgrades, and installation of planter boxes and planting.



      Hazels Creek Stormwater Treatment Project- Starting
Monday, June 20, Freya Street will be closed from 37th Avenue to
Palouse Highway through early/mid-July. Signs are up to notify drivers. This project is constructing a stormwater treatment system with disposal ponds and stormwater
piping.
37th Avenue, Regal Street to Custer Street- Due
to the closure on Freya Street for the Hazel’s Creek Project, 37th
Avenue will be closed east of Havana Street to Custer Street. The closure will
NOT impact the intersection of 37th and Havana.
Monroe/Lincoln Street Couplet, 8th
Avenue to 2nd Avenue- 
Work
on Monroe Street from 4th Ave south to 8th Ave continues. Crews
will close Monroe and Lincoln completely starting Monday evening, June 20. Detours will be
in place. The current two way traffic on
Lincoln will remain open between 4th Avenue and 6th Avenue.  Access along 7th will be provided through the work zone, but on unpaved surfaces. Monroe between 14th
and 8th Avenue will remain open for local traffic to serve the businesses and
residents in that area.  The detour for through
traffic will be along 14th Avenue and Bernard/Washington/Stevens and 2nd and
3rd Avenue. This
phase of construction is expected to last 3 to 4 weeks.  Once this phase
is complete, Monroe will be opened to traffic southbound.  Northbound
traffic will continue to be detoured until the project is complete. More paving on Monroe Street is set
for Friday, June 17.  
·    Monroe and Lincoln Street, Main Avenue to 2nd Avenue- Monroe is one lane for water infrastructure work
at the intersections of Sprague, 1st Avenue and Riverside. East/west traffic
has  lane restrictionsThis is a full depth roadway replacement and
full depth replacement between curbs on Lincoln Street and Monroe Street; Main
Avenue from Monroe Street to Lincoln Street; and Monroe Street from Spokane
Falls Boulevard to Main Avenue. Some minor curbing and ADA curb ramps will be
installed where necessary.
2016 Street Maintenance Curb Ramp Project- Work
continues on Lyons Avenue from Perry St. to Pittsburg Street to construct ADA-compliant ramps.
Ben Burr Trail and Connection to the Centennial Trail- Work
continues along the trail at Fiske and 11th Avenue with work
progressing to the north. This
project will design and construct a shared use paved trail connection for
bicyclists and pedestrian as well as security lighting installation. The
project will be from the Centennial Trail at the Gonzaga Bridge southeast of
Erie Street and continue to Liberty Park where a connection will be made to
the existing Ben Burr Trail.  The trail will then continue on the existing
Ben Burr Trail to the trailhead immediately south of Underhill Park.
Bridge Avenue and Monroe Street CSO Work-  Summit
Blvd/Bridge Avenue is closed to traffic. Rock
blasting continues. Lincoln has one northbound lane
open. Lincoln southbound is closed at Broadway. This
project will construct a Combined Sewer Overflow Tank (CSO) tank and the
necessary piping for our Cleaner River Faster Program.
·    Pettet Drive/TJ Meenach Combined Sewer Overflow (CSO 12) Project- Pettet Drive is closed to traffic until November. The clover leaf that services TJ
Meenach, Down River and Pettit Drive (three out of the four legs) is in service. The leg that comes off of Pettit northbound re-directs citizens to Northwest Blvd. Vehicles traveling
southbound on Down River Drive have two options; enter onto TJ Meenach or continue under the bridge and turn
uphill to Northwest Blvd. This
project will build a 690,000 gallon storage facility and connections to
existing CSO Basin 10 outfall. Work also includes repaving of Pettet
Drive and pedestrian/bike trail construction.

Rowan Avenue Improvements from Driscoll Boulevard to Monroe Street- Rowan Avenue from Alberta to Monroe
Street is closed.  The
intersection of Alberta, Belt, Ash, and Maple will remain open to north and
southbound traffic. Ash southbound, and Maple northbound at Rowan are reduced to one lane southbound or northbound respectively. This
project is for reconstruction work from Driscoll Blvd. to Monroe Street. The
project also includes installation of bike lanes, filling sidewalk gaps and
replacing water lines.

Translate (Traducir/Перевод) »