SPOKANE VALLEY
Appleway Trail, Pines to Evergreen- Construction of a pedestrian trail. Construction is expected to last through August, with possible single lane closures both northbound and southbound on Pines Rd. The shoulders on McDonald Road may be closed at times too.

12th Ave., Bowdish Rd to Wibur Road- Sidewalk project. Road closed and a pedestrian detour is in place.

Euclid Ave. between Flora Rd. and Tschirley Rd.- Road/sewer project. Intermittent lane closures for shoulder work. Flaggers on site.

Flora Rd. between Euclid Ave. and Dalton Ave.- Road/sewer project. Intermittent lane closure between Euclid Ave. (West) and Dalton Ave. for shoulder work. Flaggers on site.

Lenora between Collins Rd. and Vercler Dr., Collins Rd. from Lenora to 31st, and Vercler Dr. to 31stGas main replacement. Intermittent road closure.

Skipworth Rd. between 23rd Ave. and 27th Ave.- New waterline installation. Full road closure with detour signs posted.

SPOKANE CITY
37TH Avenue, Regal Street to Custer Street-
37th Avenue is closed between Regal Street and Ray Street; the Ray Street intersection is closed to reconstruct the road, curbs, sidewalk, bike lanes, stormwater piping, and a water main.

Adams Street Combined Sewer Overflow (CSO) 24 Project- Phase 2 construction is underway, along with Phase 3; installation of a new watermain in Riverside, and deep sewer piping in Riverside and Sprague. Adams Street between 1st and Sprague Avenue is reduced to one lane on the east side of the road. There is no on street parking.  1st Avenue is reduced to one lane eastbound in the furthest south lane. There is no on street parking from Cedar to just short of Jefferson Street. Sprague Avenue is closed to all westbound traffic from Jefferson to Cedar. No on street parking is permitted from Jefferson to Cedar Street, with the exception of those currently available. Westbound Riverside is open to traffic and serves as the detour route for the Sprague Ave. closure. Eastbound Riverside will remain closed from Cedar to Jefferson Street. Local access and parking is permitted via westbound Riverside.

Barnes Road from Strong Road to Phoebe Street- Strong Road from Rustle to Phoebe is closed to traffic to install a water line, new pavement, curb, sidewalk and drainage facilities.

Bridge Avenue and Monroe Street CSO Work– Summit Blvd./Bridge Ave. is closed to traffic. Lincoln has one northbound lane open.  Lincoln southbound is closed at Broadway. This project will construct a Combined Sewer Overflow Tank (CSO) tank and piping.  

Downtown Bicycle Network Phase III– Phase 3 of the Downtown Bike Network has begun. Expect lane restrictions including limited parking at Sprague/Riverside Avenue from Bernard to Maple Street.  1st Avenue from Walnut to Bernard Street

Division Street Gateway Project, 3rd Avenue to Spokane Falls Boulevard- Phase 2 of construction is near completion. This phase includes lane closures along the west curb lanes from 3rd Avenue to Sprague Avenue on both Division and Browne Street. Phase 3 is underway, with lane closures along the east curb lane from Sprague to Spokane Falls Boulevard on both Division and Browne Street. This project includes electrical conduit replacement, stormwater updates, asphalt patching, curb and sidewalk replacement and landscaping.

Hayford Force Main Replacement/West Plains Chlorine Injection Station– Construction has closed Hallett Road between Thomas Mallen Road and Westbow Road. A detour is in place. This project includes replacing 950-feet of 8-inch PVC pipe with iron pipe and construction of a chlorine injection station.

Liberty Park, Combined Sewer Overflow Tank 33-1- Work continues with traffic impacts on 5th Ave. from Arthur to Perry and Denver and Celesta. This work is to construct a 2 million gallon Combined Sewer Overflow Tank.

Monroe and Lincoln Street, Main Avenue to 2nd Avenue– Work resumes on this project Monday, July 10. There will be two lane closures along the west curb lanes of Monroe and Lincoln Street from Main to 2nd Avenue. Crews will be working on concrete corner bulb-out revisions/repairs and adjusting iron in preparation for the final lift paving and striping.

Avista is currently working on infrastructure upgrades on the corner of 1st Avenue and Lincoln Street. There are lane closures in place with flaggers and traffic control.

    • Around 7:30 a.m. Avista will close the far west lane of Lincoln Street and north turn lane of First Avenue.
    • After morning traffic around 8:30 – 9 a.m. Avista will expand the closure to include two far west lanes on Lincoln Street until 3 p.m.

This is a full depth roadway replacement and full depth replacement between curbs on Lincoln Street and Monroe Street; Main Avenue from Monroe Street to Lincoln Street; and Monroe Street from Spokane Falls Boulevard to Main Avenue. Some minor curbing and ADA curb ramps will be installed where necessary.

Spokane Falls Boulevard Combined Sewer Overflow Tank (CSO 26) Project- Significant downtown traffic changes on Spokane Falls Boulevard and Lincoln Street have started to accommodate construction of a 2.2 million-gallon concrete CSO tank across from the Downtown Library. Spokane Falls Boulevard from Lincoln to Monroe is closed to traffic. Lincoln Street from Spokane Falls Boulevard to Main is open with traffic redirected southbound. Lincoln is the detour for traffic coming from the River Park Square garage and Spokane Falls Boulevard.  Lincoln has two lanes of traffic, and drivers will be required to go east or west at Main Avenue.

Spokane Falls Boulevard, Riverfront Park Construction- New additional sidewalk closures: north side of Spokane Falls Blvd. sidewalk from Howard to Post, and east side of Post St. sidewalk from Spokane Falls Blvd. to Parking Lot 6 before the Post St. Bridge. Detours to alternate-side sidewalks are posted. The closures will be in place for a few months.

Sprague Avenue, Helena Street to Stone Street– Work on Phase I of this project, Sprague Avenue between Altamont to Napa is expected to complete in mid-July. In an effort, to accelerate the completion of this project, Phase II has begun, spanning Sprague Avenue just west of Napa to just west of Helena. Work for this project includes a full street reconstruction, partial sidewalk replacement, bumpouts, landscaping, pedestrian lighting, and utility replacement.

TJ Meenach Combined Sewer Overflow Tank, CSO I-03– Construction on this CSO tank located to the east of TJ Meenach Drive, below Northwest Boulevard continues.  There are lane restrictions on TJ Meenach Drive. There is one lane southbound and two lanes northbound. TJ Meenach Drive will be fully closed from Monday, July 24 to Monday, September 11. TJ Meenach from north of the bridge to Northwest Boulevard will be closed until late August.

This project will construct a 1.4 million gallon Combined Sewer Overflow Tank (CSO) tank and the necessary piping for our Cleaner River Faster Program.

Upriver Drive Combined Sewer Overflow Tank, CSO 41- Upriver Drive is now open from west of Freya to east of Rebecca.  Rebecca remains closed to from Upriver Drive to south of Ermina for work on the CSO Tank.  A detour is in place for the Centennial Trail.

WSDOT North Spokane Corridor (NSC)- WSDOT closed Marietta Avenue from Ralph to Greene Street for North Spokane Corridor (NSC) work. The Marietta Avenue intersections at Ralph and Greene Street will not be affected. The North Spokane Corridor will connect I-90 on the south end and US 2 and US 395 on the north end.

WSDOT
I-90/Division Street to Altamont Street- Repair bridge joints and bridge approach concrete slabs On Wednesday, July 5 beginning at about 10 p.m., westbound I-90 will be reduced to one lane for preliminary set-up. All westbound lanes reopen at about 5 a.m. Thursday morning.  Then beginning about 8 p.m., Thursday evening, July 6, westbound I-90 will be reduced to two lanes from Altamont Street to Division Street through July 18. Westbound drivers should expect slow traffic, congestion, and delays. All ramps will remain open.

I-90 Eastbound/Liberty Lake Interchange- Liberty Lake Road restoration. Be alert for congestion and delays at the I-90 eastbound on and off ramps, Appleway, and Liberty Lake Road intersection.  Work hours are 7 p.m. to 5 a.m.

SR 904 Paving- Asphalt paving and sidewalk ADA improvements. Be alert for some lane and sidewalk restrictions. Paving scheduled to start today, Thursday, June 29.

SPOKANE COUNTY
Market Street, Houston to Lincoln-
Installing curb, sidewalk, ramps, catch basins, drywells, swales, sewer pipe, and repair and replace asphalt. One lane in each direction remains open with a reduced speed limit of 25 miles per hour.

Monroe Street Improvements (Francis to Greta)- Removing/abandoning existing drainage structures, installing catch basins, pipe, sidewalk, curb, reconstructing a traffic signal, asphalt grind, repair and repave. Monroe is closed from Francis to Wall with a detour in place. Wall from Monroe to Greta is also closed.

Monroe Street Swales (Country Homes Blvd-Cedar & Excel)- Repair and repave asphalt and install curb, sidewalk, catch basins, drywells, sewer pipe. Expect delays through June 30.

Ritchey Road Bridge- Removal of the existing bridge and replace with new structure. Road closed with detour in place.

Translate (Traducir/Перевод) »